The Projects
The following is a summary of the proposed projects to be performed under the terms and conditions of this Contract Document. Each Bid Item shall include bituminous concrete material, hauling, placing, fine grading, compacting, sweeping, cleaning, keying ends, traffic apron transitions, traffic control and all else necessary to complete the items. All work shall be done in a workman like manner in conformance with all local, state and federal laws, ordinances and regulations. A one (1) year warrantee for all materials and workmanship shall be provided, commencing from the end of the project. Invoices shall include slip numbers and tons used for each roadway or sidewalk.
The following project descriptions are for illustrative purposes only and do not commit the Owners to perform the work described or to limit work performed under the terms, conditions and specification contained in this document to only those projects described below. The Owner reserves the right to change project scopes prior to the issuance of Purchase Orders against this Contract.
Item #3 Bituminous Concrete Full Width Pavement New (4") (2" of 3/4" base & 2" of 1/2" wearing)
Location | Approximate Tons |
College Street | 390 |
Total Item #3 | 390 Tons |
Item #10 Bituminous Concrete 1/2" Shim / Overlay (1" single pass)
Location | Approximate Tons |
Curtis | 150 |
Dresden | 120 |
Bridgeman | 76 |
Woodmore | 155 |
Highland | 108 |
Fairview | 57 |
Meadow | 212 |
Foxfield | 82 |
Ruddsboro/reclaim wearing course | 1174 |
Total Item #10 | 2,134 Tons |
Item #10A Bituminous Concrete 1/2" Shim / Overlay (1 1/2" single pass)
Location | Approximate Tons |
Summer Street | 120 |
Total Item #10A | 120 Tons |
Item #11 Bituminous Concrete Shim 1" of 1/2" - Overlay 1" of 1/2" top
Location | Approximate Tons |
East Wheelock – Park to Grasse Rd | 2061 |
Verona (to Willow) | 574 |
Willow (Verona to Rip) | 204 |
Butternut/Wren | 266 |
Total Item #10 | 3,105 Tons |
Item #12A Bituminous Concrete Sidewalks 1" of 3/8" Top
Location | Approximate Tons |
Dresden Rd | 40 |
Lebanon Street Park to Crowly | 25 |
Lebanon Street Barrymore to Storrs | 25 |
Lebanon Street Greensboro to Pump Sta | 65 |
S. Balch to Valley to Park | 30 |
E. Wheelock Park to Verona | 70 |
Total Item Sidewalks | 255 Tons |